Planning Timescales

  • Submission of Proposal of Application Notice April 2013
  • Public Events - July-13
  • Submission of Planning Application – October 2013
  • Submission of Scheme 2 Application – January 2014
  • Scheme Re-Advertisement – January 2014
  • Planning approval received – March 2014

Upcoming dates (approximates):

  • Outline Business Case approval – October 2014
  • Financial Close –October 2014
  • Building work to start on site – November 2014.
  • Phase one project completion – late 2016.

Last Reviewed: 09/09/2014