Construction Update: February 2016

The concrete frame, floors and core works continue across all available construction areas. The first stages of the external wall works (facing the Chancellors Building) are moving on, with both framing, boarding and windows being installed. Cladding will follow on in due course.
 
Internally, the setting out of partitions, fixing of electrical cables, ventilation and internal flights of stairs are also being developed.
 
Within the basement, all main concrete pours are now complete and the energy centre basement walls will soon be finished.
 
Out with the site boundary, preliminary works have begun on facilitating public utilities and services connections from the A7 (Old Dalkeith Road) and at the Anne Rowling Building within the RIE Campus.