Milestone Dates 
 
  • Legal agreement to buy the land - July 2006
  • Outline planning permission granted - Oct 2008
  • Governme​nt approval granted for outline business case - Dec 2008
  • JM Architects appointed - Jan 2009
  • Dawn Construction appointed to deliver Musselburgh PCC - Nov 2009
  • Full planning permission granted - Jan 2010
  • Roman remains found following site excavation - Jan 2010
  • Relics from the Iron Age and Roman times dating from 6,000 years ago are discovered on site - Nov 2010
  • Work continues on Musselburgh PCC - Jan 2011
  • Site completion - April 2012
  • First patients admitted - April 2012
  • Official opening - August 2012